Work continues on the SARA EPC 02/02/18

Last October, we began work to replace the main high-voltage switchgear for substation 1 of the SARA (Société Anonyme de Raffinerie des Antilles) in Martinique.

This replacement is being carried out live, with the station’s dependent units continuing to operate during the works. So far, the first part of the board has been installed and powered up. The works are scheduled for completion in the first quarter of 2018.

The SARA is 71% owned by the company Rubis and owns a refinery in Martinique, as well as hydrocarbon depots in Jarry, Guadeloupe, and Kourou and Dégrad des Cannes in French Guiana.

Montage du nouveau tableau (tableau blanc) pendant que l’ancien tableau (tableau vert) demeure en fonctionnement.